Client

Mylan Germany GmbH

Location

Troisdorf

Services

Turnkey Contractor Services (LPH 3–8)
Overall project management, project oversight, construction management
Laboratory (Safety Level S1)

area

approx. 1.954 m² GFA
approx. 3.700 m³ GV

Construction Costs

approx. € 1.30 million net

Project Term

October 2018 – July 2019

Construction period

February 2019 - July 2019

CP Bauteam carried out the renovation of an existing building for Mylan GmbH, converting it into modern quality control laboratory spaces. As part of the project, office spaces were converted into laboratory areas, and the building’s technical systems and fire protection measures were comprehensively upgraded. The work was carried out while operations continued, requiring precise construction scheduling to ensure that the adjacent laboratory and office areas remained fully operational at all times.