Client

BOLDER Arzneimittel GmbH & Co. KG

Location

Cologne

Services

General Contractor Services (Phases 5–8)
Overall Project Management, Construction Management, Project Coordination
Structural Work, Interior Finishing, Building Services, Logistics
Outdoor Facilities

Area

approx. 5.560 m² GFA
approx. 35.685 m³ GV

Construction cost

approx. 11,92 million € net

Project Term

June 2018 - December 2023

Construction Period

April 2021 - December 2023

Since relocating its production facility from Bolder in 2012 to its current location in Cologne-Marsdorf, the company has experienced steady growth. Over the years, the steadily increasing production volume led to capacity bottlenecks in various areas, particularly in the drying chambers and storage areas. To lay the groundwork for further growth, the production and storage capacities were expanded on a plot of land directly adjacent to the existing factory grounds. CP Bauteam supported the project using a collaborative construction team model, from early project development through to successful implementation. As part of the joint project management, the client’s requirements were aligned at an early stage with the technical, economic, and scheduling constraints. Through close collaboration among all project participants, planning and execution were effectively coordinated, and cost-effective and sustainable solutions were developed. Implementation took place in a two-phase process. In the first phase, the planning foundations were established, project objectives were refined, and a robust cost and schedule framework was created. The project was implemented in a two-phase process. In the first phase, the planning framework was developed, project objectives were refined, and a solid foundation for cost and schedule estimates was established. Building on these results, the construction work was carried out in the second phase. Thanks to the collaborative approach, the project objectives regarding functionality, quality, cost-effectiveness, and adherence to the schedule were successfully achieved. With the completion of the expansion, production and storage capacities were sustainably expanded, and the long-term development of the Cologne-Marsdorf site was secured.